Programme · PRG-2247
Brake Caliper Housing
TOYOTETSU INDIA AUTO PARTS (P) LTD · Part BRK-2247-A · PPAP Level 3 · Programme Manager view
Launch
2025-09-15
0 days to go
Status
AMBERDays to Launch
0
Gates Signed
2/5
G3 in review
Open Actions
2 open
3 overdue
High Risks
2
APQP Stage-Gate Progress
2/5 gates signedPlanning
100% · 10/10
Product Design
100% · 10/10
Process Design
68% · 7/10
Validation
0% · 0/10
Launch
0% · 0/10
Phase 1 · Planning
100% · 10/10
Phase 2 · Product Design
100% · 10/10
Phase 3 · Process Design
68% · 7/10
Phase 4 · Validation
0% · 0/10
Phase 5 · Launch
0% · 0/10
Stage-gate governance: A phase cannot exit until every mandatory deliverable is complete, RPN-critical actions are closed, and the gate is signed by the named approver. Gates lock the snapshot — nothing edits backwards.
Phase Completion Trend
Complete Floor Plan & Process Layout drawing
Suresh Kumar · Due 2025-06-30 · Phase 3OVERDUE
Submit Packaging Specification to customer for approval
Suresh Kumar · Due 2025-06-20 · Phase 3OVERDUE
Finalise Supplier PPAP requirements for 3 sub-suppliers
Priya Nair · Due 2025-06-25 · Phase 3
Close PFMEA RPN item: Porosity in casting (RPN 108)
Suresh Kumar · Due 2025-06-15 · Phase 3OVERDUE
Confirm MSA gauge availability for Phase 4 studies
Priya Nair · Due 2025-07-05 · Phase 4
Stage-Gate Governance
G1 · Planning Gate
Signed 2025-01-20Approver: Vikram Desai (Plant Manager)
- · Programme Plan approved
- · Feasibility committed
- · Team & RACI signed
G2 · Product Design Gate
Signed 2025-03-05Approver: Vikram Desai (Plant Manager)
- · DFMEA closed (RPN ≤ threshold)
- · Design records approved
- · Drawings released
G3 · Process Design Gate
In ReviewApprover: Vikram Desai (Plant Manager) + Customer Witness
- · PFMEA + Control Plan approved
- · Tooling qualified
- · Process flow signed
G4 · Validation Gate
LockedApprover: Priya Nair (Quality Manager) + Customer
- · MSA + Cpk targets met
- · Run@Rate passed
- · PPAP submitted
G5 · Launch Gate
LockedApprover: Rajesh Iyer (Programme Manager) + Plant Manager
- · Customer PPAP approved
- · Lessons learned filed
- · Safe-launch closed
Hard rule: a phase cannot start until the prior gate is signed. Override requires Plant Manager + Programme Manager dual approval — every override is logged and visible to leadership.
Programme Milestones
- Complete
Phase 1 Gate Approved
Phase 1 · 2025-01-20
- Complete
DFMEA Approved
Phase 2 · 2025-02-10
- Complete
Phase 2 Gate Approved
Phase 2 · 2025-03-05
- Complete
PFMEA Approved
Phase 3 · 2025-04-25
- Complete
Control Plan Approved
Phase 3 · 2025-05-10
- At Risk
Phase 3 Gate Target
Phase 3 · 2025-07-05
- Not Started
Trial Run Completion
Phase 4 · 2025-07-20
- Not Started
PPAP Submission to Customer
Phase 4 · 2025-08-10
- Not Started
PPAP Customer Approval
Phase 4 · 2025-08-25
- Not Started
SOP Mass Production
Phase 5 · 2025-09-15
Phase 3 gate delay risk — 3 deliverables overdue
Mitigation: Daily standup initiated; PM escalation to Plant Manager
Porosity defect in casting — RPN 108 still open
Mitigation: Vacuum casting trial scheduled for 10 Jun
Sub-supplier PPAP for seals not yet initiated
Mitigation: Supplier visit scheduled 30 Jun
CMM availability conflict with another programme in Jul
Mitigation: Booking confirmed for Jul 18–22 slot