Programme · PRG-2247
Brake Caliper Housing
TOYOTETSU INDIA AUTO PARTS (P) LTD · Part BRK-2247-A · PPAP Level 3 · Risk register & open actions
Launch
2025-09-15
0 days to go
Status
AMBERPhase 3 gate delay risk — 3 deliverables overdue
Mitigation: Daily standup initiated; PM escalation to Plant Manager
Porosity defect in casting — RPN 108 still open
Mitigation: Vacuum casting trial scheduled for 10 Jun
Sub-supplier PPAP for seals not yet initiated
Mitigation: Supplier visit scheduled 30 Jun
CMM availability conflict with another programme in Jul
Mitigation: Booking confirmed for Jul 18–22 slot
Complete Floor Plan & Process Layout drawing
Suresh Kumar · Due 2025-06-30 · Phase 3OVERDUE
Submit Packaging Specification to customer for approval
Suresh Kumar · Due 2025-06-20 · Phase 3OVERDUE
Finalise Supplier PPAP requirements for 3 sub-suppliers
Priya Nair · Due 2025-06-25 · Phase 3
Close PFMEA RPN item: Porosity in casting (RPN 108)
Suresh Kumar · Due 2025-06-15 · Phase 3OVERDUE
Confirm MSA gauge availability for Phase 4 studies
Priya Nair · Due 2025-07-05 · Phase 4